2021PMP考試單元測試二
- 發(fā)布: 中公PMP培訓(xùn)機構(gòu)
- 來源:PMP培訓(xùn)
- 2021-02-25 11:12:18
- 閱讀()
1. As the project manager on a software development project, your organization typically breaks up software projects four smaller phases: requirements, design and development, quality assurance, and implementation. This is an example of:
作為軟件開發(fā)項目的項目經(jīng)理,您的組織通常將軟件項目分成四個較小的階段:需求、設(shè)計
和開發(fā)、質(zhì)量保證和實現(xiàn)。這是一個( )例子:
A. A work breakdown schedule
工作分解時間表
B. A functional organization
職能組織
C. Progressive elaboration
漸進明細
D. A project life cycle
項目生命周期
2.The project manager working in a balanced matrix organization realizes that maintaining team
cohesiveness, motivation, and performance is critical to the project's success. Which of the
following skill sets should be used to manage this type of organization?
在項目經(jīng)理在一個平衡矩陣式組織工作,他意識到保持團隊凝聚力、激勵和績效對項目成功
至關(guān)重要。管理這種類型的組織應(yīng)使用下列哪一項技巧?
A.The ability to influence team members not directly reporting to the project manager
影響那些不直接向項目經(jīng)理匯報的團隊成員的能力
B.The ability to understand the various responsibilities of all team members
了解出全體團隊成員不同職責(zé)的能力
C.The ability to respond to the different motivations of team members
給與團隊成員不同激勵的能力
D. The ability to negotiate conflict between team members
協(xié)調(diào)團隊成員之間沖突的能力
3. Performing the initiating processes at the start of each phase helps focus the project on:
在每個階段開始時執(zhí)行啟動過程有助于將項目集中在:
A. Potential risks that should be identified
應(yīng)查明的潛在風(fēng)險
B. Additional requirements for the project
項目的額外要求
C. The business need for the project
項目的商業(yè)需要
D. Procurement items that may be needed in the phase
階段中可能需要的采購項目
4. Due to significant cost overruns, the steering committee terminates the project. The stakeholders do not agree with the decision, because they believe the true value of the project objectives cannot be measured in monetary terms. The steering committee chairperson asks the project manager to prepare a lessons learned presentation for a joint meeting of the key stakeholders, the sponsor, and the steering committee. The chairperson expects this activity will reduce the tension among the departments. The project manager must travel to corporate headquarters to give the presentation. What should the project manager update?
由于顯著的成本超支,督導(dǎo)委員會終止該項目。項目干系人不同意這個決定,因為他們相信項目目標的真正價值不能用金錢來衡量。督導(dǎo)委員會主席要求項目經(jīng)理準備經(jīng)驗教訓(xùn)并在由主要利益相關(guān)者,贊助商,及督導(dǎo)委員會組成的聯(lián)席會議上做展示。主席預(yù)計這項活動將減少各部門之間的緊張關(guān)系。項目經(jīng)理必須到公司總部給演示。項目經(jīng)理該如何準備?
A. Project scope statement
項目范圍說明書
B. Risk management plan
風(fēng)險管理計劃
C. Organizational process assets
組織過程資產(chǎn)
D. Project management plan
項目管理計劃
參考答案:
1. 答案:D。A project life cycle is a series of phases that a project passes through.
2. 答案:D,通過開放和有效的溝通、在團隊成員中建立信任、以建設(shè)性方式管理沖突,以及鼓勵合作型的問題解決和決策制定方法,可以實現(xiàn)團隊的高效運行。此題選擇最佳答案,題干當中說明這是一個平衡矩陣,首先要排除掉選項 A\C,平衡矩陣型組織雖然承認全職項目經(jīng)理的必要性,但并未授權(quán)其全權(quán)管理項目和項目資金。
3. 答案:c,A), B), and D) are all planning processes.
4. 答案:C,題干中,明顯指出需要準備的會議材料為經(jīng)驗教訓(xùn),則應(yīng)當迅速判斷經(jīng)驗教訓(xùn)會存檔在何種文檔中,由此判斷應(yīng)當選擇組織過程資產(chǎn):任何或全部與過程相關(guān)的資產(chǎn),來自任一或所有參與項目的組織,可用于幫助項目成功。這些過程資產(chǎn)包括正式和非正式的計劃、政策、程序和指南。過程資產(chǎn)還包括組織的知識庫,如經(jīng)驗教訓(xùn)和歷史信息。
>>本文地址:
注:本站稿件未經(jīng)許可不得轉(zhuǎn)載,轉(zhuǎn)載請保留出處及源文件地址。
上一篇:2021PMP考試單元測試一
中公PMP備考交流平臺
-
PMP微信交流群
-
PMPQQ交流群